Miller Creek Phase 3

Utah


Miller Creek


Price


Link ↗


Sep. 15, 2020


1500


50


Project Goals and Objectives

This project was implemented as post-fire recovery of stream habitat. This project was funded by the Watershed Restoration Initiative. Project partners include a Private landowner, Utah Division of Wildlife Resources, Trout Unlimited, Sageland Collaborative, and the U.S. Fish and Wildlife Service.

Structure Construction Elements

We built beaver dam analogs (BDAs) using untreated wood posts (2-4" diameter) pounded into the stream-bed at the height of the ordinary high water mark and then filled in by volunteers using on-site materials including sustainably harvested willow branches, mud, rocks, and clumps of sod.