Poison Meadow- Golden Trout Wilderness; Inyo National Forest- Phase 2

Anabranch Solutions Design and Construction
Trout Unlimited Funding and Coordination
This project needs a nice cover photo

California


Unnamed


Upper Cottonwood Creek


Oct. 01, 2024


300


25


Project Goals and Objectives

In 2023, 30 structures were implemented in Poison meadow to address headcut development and advancement, promote aggradation, increase floodplain connectivity, and raise the water table elevation. In 2024, we revisited Poison meadow and maintained and enhanced 25 structures to further our above goals.

Structure Construction Elements

A combination of BDA, PALS and Hybrid structures were used throughout the meadow. In areas where digging was not possible, hybrid structures were used to promote similar results as BDAs. We also implemented rock Zeedyk structures to address headcuts.