Horseshoe Meadow-Phase 3

Anabranch Solutions Design and Construction
Trout Unlimited Funding and Coordination
This project needs a nice cover photo

California


Unnamed Tributary to Cottonwood Creek


Upper Cottonwood Creek


Oct. 01, 2024


245


10


Project Goals and Objectives

In 2022, 10 structures were implemented as a pilot study. In 2023, we returned to maintain and enhance structures. In 2024, we returned again in order to support overall objectives, which were to Objectives were to increase in-channel aggradation, increase floodplain connectivity, create deep water habitat and increase instream complexity.

Structure Construction Elements

A combination of BDA, PALS and Hybrid structures were used throughout the meadow. In areas where digging was not possible, hybrid structures were used to promote similar results as BDAs.

Project Photos
This project needs a nice cover photo

Cover Photo

Project Location