Basin-Mahogany Creek Stream Restoration Phase II


Project on Basin Creek, Mahogany Creek

Utah


Basin Creek, Mahogany Creek


Raft River Watershed


Oct. 15, 2015


500


15


Project Goals and Objectives

Evaluate and maintain BDAs built in September 2014. Project goals were to improve instream habitat for Yellowstone Cutthroat Trout and create deep water habitat for beaver translocation.

Structure Construction Elements

Structures built with straw bales in 2014 had degraded, additional posts and willow (harvested immediately downstream of project area) were used to maintain/rebuild existing BDAs.